The ACI 318 direct design procedure for two way slabs leads one to provide much more steel in the strips running between columns than in the other portions of the slab. Why ?
I don't know direct design ,perhaps you want to say that in solid slab design (not the flat slab ) you are using ready-made tables of coefficient for finding moment & shear based on long & short span ratio & edge fixidity condition of slab,in this regard I will only remind you that negative moment at support is higher than middle span positive moment.
In flat slab construction , there is no beam .In solid slab there is a beam running column to column & carrying all load of adjoining slabs up-to half of span on both side of beam.In flat slab since there is a column strip in place of beam & this column strip thus designed for higher rigidity & act as beam as it runs between columns.
Answers & Comments
Verified answer
I don't know direct design ,perhaps you want to say that in solid slab design (not the flat slab ) you are using ready-made tables of coefficient for finding moment & shear based on long & short span ratio & edge fixidity condition of slab,in this regard I will only remind you that negative moment at support is higher than middle span positive moment.
In flat slab construction , there is no beam .In solid slab there is a beam running column to column & carrying all load of adjoining slabs up-to half of span on both side of beam.In flat slab since there is a column strip in place of beam & this column strip thus designed for higher rigidity & act as beam as it runs between columns.
Refer